| Project name | Bien Hoa Airbase Dioxin Remediation Project – Phase 1 |
| Package | Phase 1 Processing (TP1) |
| Location | Bien Hoa, Dong Nai Province |
| Owner / Main Contractor | Nelson Environmental Remediation USA LTD |
| Time | 29/09/2025 |
| Status | Ongoing |
| Sector | Environmental & Energy Works / Technical Infrastructure |
The Bien Hoa Airbase Dioxin Remediation Project – Phase 1 is being implemented in Bien Hoa, Dong Nai Province. Under Phase 1 Processing – TP1 Package, VINA E&C is undertaking construction, steel structure and supporting infrastructure works for treatment, storage and functional facilities of the project.
According to the latest update, the overall progress of TP1 Package has reached 56.3%. Key work items currently being focused on include corner walls, parapet, ramp, backfill, geotextile installation, HDPE covering, gabion works, L-block and T-block installation, and steel structure works.
Since early May, additional manpower has been transferred from CW1 Package to TP1 Package, with further reinforcement planned in the coming period to accelerate the implementation of key construction activities.
In parallel, steel structure works, precast component installation and supporting infrastructure works continue to be implemented on site. VINA E&C remains focused on progress control, safety, quality and close coordination with relevant parties throughout the execution process.
Moving forward, VINA E&C will continue to follow the construction plan, strengthen site resources and coordinate closely on site to complete TP1 Package work items in accordance with project requirements.



VINA E&C has been awarded a construction contract for the Stavian Aluminium Packaging Foil Rolling Plant at Quan Do Industrial Cluster, Doan Dao Commune, Hung Yen Province. The project adds to the Company’s industrial construction portfolio.
Under the theme “Healthy Today – Confident Steps Tomorrow”, VINA E&C is rolling out its 2026 employee health check-up programme across its offices and project sites. Scheduled for completion before 25 October 2026, the programme reflects the Company’s commitment to employee health and well-being.
On August 16, 2026, VINA E&C joined LSP and its partners in the “Proactive Prevention and Community Health Care 2026” program in Long Son Commune, contributing to better access to health care and promoting shared responsibility for a healthier community.