Lac Hoa II Wind Power Plant


VINA E&C participated in Lac Hoa II Wind Power Plant in Vinh Chau Town, Soc Trang Province.

Construction of Infrastructure and Turbine Erection Yard.

Partner/Project Owner: Lac Hoa 2 Wind Power Company Limited.

Implementation period: 2021–2024.

Scope of work
• Site clearing, cleanup and removal of organic topsoil.
• Site grading and preparation.
• Temporary access roads and internal roads.
• Wind-turbine erection yard.
• Equipment laydown areas.

The project demonstrates VINA E&C’s capabilities in construction planning, quality control, safety and schedule management for energy infrastructure.

Related projects

Stavian Aluminium Packaging Foil Rolling Plant

Located in Quan Do Industrial Cluster, Doan Dao Commune, Hung Yen Province, the Stavian Aluminium Packaging Foil Rolling Plant is developed by Công ty Cổ phần Stavian Bao bì Nhôm. VINA E&C participates in the project as a construction contractor.

Tan Cang Nhon Trach ICD Warehouse

VINA E&C serves as the main contractor for Package No. 07 – Construction of the Warehouse and Technical Infrastructure under the warehouse investment project at Tan Cang Nhon Trach ICD. The project comprises a 6,750 m² warehouse together with surrounding roads, yards, slope protection and integrated technical infrastructure.

CARBON FIBER AND MATERIAL FACTORY - CONSTRUCTION UTILITIES

VINA E&C participated in Construction of Main Technical Infrastructure – Area A in Phu My, Ba Ria – Vung Tau, including soft soil treatment using the phd method over approximately 91,600 m² and site grading and preparation.

Bio-BDO Biological Products Factory

VINA E&C participated in Soft Soil Treatment Package in Phu My Town, Ba Ria – Vung Tau Province, including soft soil treatment using the phd method over approximately 251,000 m².

CARBON FIBER AND MATERIALS FACTORY PROJECT

The Hyosung Advanced Materials Factory project in Ba Ria-Vung Tau Province, undertaken by VINA E&C as the main contractor, focuses on the treatment of a 91,613 m2 area of land using the high-quality PHD method. The project implementation ensures both quality and progress in the work. The goal of the project is to establish a modern and sustainable production infrastructure in the region, contributing to the local economic development and creating numerous employment opportunities.

VARD PLANT EXPANSION – UTILITY INFRASTRUCTURE SYSTEMS

VINA E&C participated in the construction of utility infrastructure systems for the VARD Plant Expansion Project at Dong Xuyen Industrial Park, Vung Tau City. The scope included drainage systems, MEP trenches and manholes, road-crossing pipes, a 300 m³ underground water tank and a pump station building.

Package A2 – Long Son Petrochemicals Complex

VINA E&C participated in Package A2 – Structural Construction Works (Package 1) under the Long Son Petrochemicals Complex Project. The scope included site development, reinforced-concrete tank foundations, pipe-rack foundations, structural steel works, underground piping and drainage systems.

Bulk Cargo Warehouse No. 1 – Thi Vai General Port

VINA E&C participated in the construction and installation of Bulk Cargo Warehouse No. 1 at Thi Vai General Port, Ba Ria – Vung Tau Province. The 6,424 m² facility was developed to support bulk-cargo storage and port operations.