VINA E&C Accelerates Construction Progress at Thuong Phuoc – Moc Ra International Border Gate Infrastructure Project

28.10.2026

On October 27, 2026, VINA E&C continued to mobilize manpower and equipment to advance construction activities under Packages 24 and 25 of the Thuong Phuoc – Moc Ra International Border Gate Infrastructure Project in Dong Thap Province, with a focus on safety, quality, and project progress.

Advancing Key Construction Activities

Under Package 24, sand filling works had reached approximately 154,000 out of 170,000 cubic meters, exceeding 90% of the planned volume as of October 25, 2026. Bridge construction was progressing, with concrete deck casting completed for two of seven spans. Subsequent construction activities and preparations for roadbed and pavement works were also underway.

Under Package 25, multiple construction operations continued simultaneously, including earthworks, roadbed compaction, sand filling, embankment construction, geotextile reinforcement, and ground improvement.

Bridge works included reinforcing steel installation for the T4–T5 deck span, installation of concrete cover slabs, and related structural activities. Preparations for technical infrastructure and finishing components were also in progress.

Addressing Challenges and Maintaining Progress

The project continues to face challenges related to construction material availability, particularly crushed stone aggregates required for road construction.

VINA E&C is coordinating with relevant departments to secure additional material supplies, optimize resource allocation, and prepare supporting components to maintain construction continuity.

On October 27, Mr. Vu Van Liem, General Director of VINA E&C, visited the construction site to review actual progress and discuss practical solutions with the project management team.

Through proactive coordination and resource mobilization, VINA E&C remains committed to advancing construction activities while maintaining safety and quality standards.

Upon completion, the Thuong Phuoc – Moc Ra International Border Gate Infrastructure Project is expected to strengthen regional transport connectivity, facilitate cross-border trade, and contribute to the socio-economic development of Dong Thap Province.

VINA E&C – Sustainable links - Building the future.

Related news

28.10.2026

Highlights from VINA E&C’s 2026 Annual Health Check-up Program

Continuing its commitment to employee well-being, VINA E&C organized its 2026 Annual Health Check-up Program throughout October 2026 at its offices, construction sites, and project locations.

20.10.2026

VINA E&C Breaks Ground on 2.65-ha CBU Yard Expansion at SPCT

On October 20, 2026, VINA E&C officially broke ground on the 2.65-hectare CBU Yard Expansion Project at Saigon Premier Container Terminal (SPCT), Hiep Phuoc, Ho Chi Minh City, further strengthening its presence in port infrastructure construction through the Design & Build (D&B) delivery model.

05.10.2026

VINA E&C Wins Construction Contract for Stavian Aluminium Packaging Foil Rolling Plant in Hung Yen

VINA E&C has been awarded a construction contract for the Stavian Aluminium Packaging Foil Rolling Plant at Quan Do Industrial Cluster, Doan Dao Commune, Hung Yen Province. The project adds to the Company’s industrial construction portfolio.