Partner: | Long Son Petrochemical Company Limited |
Work items: | The work item includes: + Factory and spare parts warehouse + Emergency and emergency center + Canteen + Guest house + Security house + Transformer station + Sugar system and technical infrastructure |
Construction time: | 2021 - Completing T5/2022 |
Package 4: Construction
Package 4: Construction (including Traffic Safety Assurance costs and contingency fees)
Construction of site leveling, landfill, drainage system, subdivision 2 (21.5ha)
Package 07: Construction of warehouse and technical infrastructure
Full package of design, appraisal and assessment, construction permit application and construction of COD improvement system
Construction of level 1 leveling level 1 - Division 2 (5.2ha)
Construction of utilities
Xử lý nền đất yếu
Package XL01: Construction and installation of all equipment